View Project


Nama Proyek
Arthatel [Damkar SGA]
Deskripsi

2023.

PABX & AP


PABX PANASONIC   KX TES 824  3PTT 8 EXTENTION 1  UNIT 
TERMINAL BOX TELEPON KAPASITAS 20 PAIR 1  UNIT 
FACEPLATE DATA 2 PORT 3  PCS 
MODULAR TELEPON AMP 3  PCS 
OUTBOW DOS 3  PCS 
PESAWAT TELEPON ANALOG PANASONIC KX-T2371 2  PCS 
KABEL UTP CAT 6 1  DOZ 
KABEL UTP CAT 5 1  DOZ 
KABEL FO DROP CORE 2 CORE 150  M 
FACE PLATE FO 2 CORE + AKSESORIES SC 2  PCS 
PATCH CORD SC/UPC - SC/APC SM DUPLEX 2M 1  PCS 
PATCH CORD SC/UPC - SC/UPC SM DUPLEX 2M 1  PCS 
PIPA CONDUIT 20MM PUTIH 120  BTG 
SOK PIPA CONDUIT 20MM PUTIH 150  PCS 
KLEM PIPA CONDUIT 20MM 200  PCS 
FLEKSIBEL CONDUIT 20MM 1  ROLL 
Kabel duct 50 x 50 MM PANJANG 3 M 2  BTG 
KABEL DUCT CURVA 10 x 35MM 5  M 
Kabel duct TC 4 20  BTG 
AKSESORIES (KABEL TIES, FISHER & SEKRUP S6 RJ 45 DLL) 1  LOT 
Tgl Mulai
May 22, 2023
Tgl Akhir
May 28, 2023
Status
Done
Project Manager
Avatar PM1 .
List Kerja
# Pekerjaan Deskripsi Status Action
1 0. Survey

Done
2 A. Instalasi Kabel UTP CAT 6

3 titik ke AP (internet)

Done
3 B. Instalasi Kabel UTP CAT 5

8 titik ke telepon

Done
4 C. Instalasi Kabel FO Dropcore

backbone internet sudah selesai

Done
5 D. Instalasi Backbone Telepone

1 titik

Done
6 E. Patching PABX & Setting

Done
7 F. Splacing FO & Comitioning

4 core

Done
8 G. Pemasangan Access Point

3 titik AP

Done
9 H. Testing & Comitioning

Done
10 I. Mobilisasi

Done
Catatan Pekerja